Court fees.Russian legal calculators

Free · no registration

Penalty
for developer delay.

Periods, rates and accrual for delayed transfer of an ordinary apartment, accounting for moratoria and special caps.

1/150 of the rate

Article 6 · Law No. 214-FZ
For a citizen

For an ordinary apartment under a registered equity participation agreement and one original individual participant for personal use. Calculates late-transfer accrual under Article 6(2), Law No. 214-FZ. Unique buildings, assignments, shares and disputed acceptance require separate assessment.

Use spaces for thousands and a comma or period for decimals, for example 1 000.50. A comma is a decimal separator. Copied calculations and printouts are in Russian.

Supported contractual deadlines: 1 January 2020 to 23 November 2026 inclusive. Later dates will be available after the rate data is checked.

01 Calculation conditions

Choose answers from your documents. “I don't know” means the facts need clarification; this version does not substitute favorable assumptions.

Check uniqueness in the project documentation. Advertising does not establish it.

This version does not allocate amounts between participants or account for assignment of claims.

The calculator does not interpret a quarter or a period after commissioning, or verify the validity of a deadline change.

If actual transfer and the act have different dates, or there is a dispute about defects or evasion, legal review is needed first.

Includes special territorial regimes. If unknown, this version cannot confirm a calculation.

02 Price and transfer deadline

The full unchanged contract price, not market value, outstanding debt or only escrow funds. The technical limit is 1 trillion ₽, not a limit on legal rights.

Use the legally verified last day, accounting for valid agreements and deadline rules. If the contract specifies a quarter or a period after commissioning, or a change is disputed, determine the date first. The calculator neither establishes nor automatically extends it. Deadlines from 1 January 2020 are supported.

03 Transfer or calculation date

Penalty by formula for the selected period

—

Enter conditions, contract price and dates.

Accrual before any court reduction. Penalties already paid or recovered are not deducted. Fines, losses and other claims are excluded from the total.

Accrual and payment

Deferral of payment does not mean zero accrual. Resolution No. 2227 changed certain deferrals but did not extend the ordinary non-accrual period into 2026. Resolution No. 326, paragraph 1, applies its listed requirements to enforcement claims presented to the developer before it took effect. Law No. 46-FZ Article 18(4) separately allows an application to court for deferral or installments; part 5 extends certain earlier court deferrals through 31 December 2026 without an extension application. These provisions do not automatically defer every new claim, prohibit filing, or promise payment on 1 January 2027. Check applicability and the stage of your case separately.

Next steps

Check the registered contract, valid amendments, project documents, acceptance notices, transfer act and payment records. Check whether the period overlaps amounts already paid or recovered. Save the table for a separate claim and assessment. The calculator does not decide whether a deadline change is valid, whether acceptance was evaded, the limitation period, or the amount a court will award.

How this is calculated

Use the full unchanged contract price and verified last transfer day. Delay begins on the next day; the uncontested transfer or calculation day is included. Weekends within the delay are counted. The Central Bank base rate is fixed on the last contract day, not recalculated at each later rate change or replaced with the rate on transfer or today (Supreme Court position in Constitutional Court Review 2024, paragraph 73).

The calculator excludes 3 April 2020–1 January 2021, 29 March 2022–30 June 2023 and 22 March 2024–31 December 2025 inclusive. For the first interval it follows the final position in answer 12 of Supreme Court COVID-19 Review No. 3 on future-awarded penalties under the same Article 6(2): Resolution No. 423 says “until 1 January”, while the Supreme Court answer says “through 1 January”. Another approach in an individual dispute is not ruled out.

For non-excluded days, a 9.50% rate cap applies from 25 February 2022 through 30 June 2023 and a 7.50% cap from 1 July 2023 through 31 December 2025. The lower of the base rate and cap is used; excluded days take precedence. Outside these periods the base rate applies. For a citizen: contract price × rate in percent / 100 × days / 150, without dividing by 365 or 366. Exact accruals are added and the total is rounded once to the kopeck, half up; any difference from displayed rounded rows is shown separately.

Article 333 reductions, fines, losses, moral harm, termination and defects are not calculated. The 5% cap for certain unique properties and 3% cap for finishing claims are not general caps for ordinary late-transfer penalties. Legal review: 24 November 2026; next review due by 16 December 2026. Without updated rules, calculation is blocked after that date. This does not terminate legal rights. A 2027 calculation requires separate review.

Questions about the calculation

Which amount should I enter: the price or escrow balance?

The base under Article 6(2) of Law No. 214-FZ is the contract price, not market value or just escrow funds. This version accepts one full, unchanged price; if it changed, review the contract and calculation separately.

Why use the rate on the deadline rather than today?

The method uses the rate on the contract performance date, or the last day where a period is specified. The Supreme Court position appears in paragraph 73 of the Constitutional Court's 2024 review. Special caps apply separately; the transfer-day or current rate is not substituted for the base rate.

Which periods are excluded?

For the supported ordinary penalty, 3 April 2020–1 January 2021, 29 March 2022–30 June 2023, and 22 March 2024–31 December 2025 are excluded, inclusive. The first endpoint follows the final position in answer 12 of Supreme Court COVID-19 Review No. 3 concerning penalties awarded for the future; the method above explains the original resolution's wording. An applicable moratorium cannot be switched off.

Does accrual resume in 2026?

In the reviewed version, the ordinary excluded period under Article 6(2) ended on 31 December 2025. For supported calculations the base obligation rate applies again from 1 January 2026. Resolution No. 2227 concerning deferral did not extend that non-accrual period. Future changes and 2027 rules are not assumed.

Is the transfer day included?

This version includes the day of uncontested actual performance under Supreme Court Plenum No. 7, paragraph 65. Accrual starts after the verified deadline. A unilateral act, disputed date, refusal, defects or evasion requires separate legal review and no ready amount is given here.

What if the contract specifies a quarter or time after commissioning?

First establish the legally significant last day, considering valid agreements and deadline rules including Civil Code Article 193. The calculator does not interpret these clauses or extend dates automatically. A developer's letter alone does not replace a valid contract amendment.

Is there a general 3% or 5% cap?

These limits concern different special regimes: 5% for specified unique objects under certain conditions, and 3% for certain finishing claims. Article 10(4) expressly excludes penalties under Articles 6(2) and 6(2.1) from the finishing cap. Unique buildings are outside this version; it does not impose a general cap on ordinary transfer delay.

Can it calculate assignments or multiple participants?

This version covers one original individual participant and an ordinary apartment. Assignments, shares, multiple participants, business purposes and special regimes need separate calculation. This model limit does not mean there is no right to a penalty.

Does zero mean no claim is possible?

No. Zero may mean no delay, a fully excluded period, or a positive exact accrual rounded to zero. The reason is shown. Unsupported or unknown circumstances yield a dash instead of zero; other claims are not assessed.

Can I immediately receive the calculated amount?

This is a formula accrual under confirmed conditions, not a court award or payment date. Possible Civil Code Article 333 reduction, amounts already paid or recovered, deferrals and enforcement stage must be checked separately. A deferral does not imply automatic payment on 1 January 2027 or cancel accrual for all of 2026.

Read about recovering a developer delay penalty (in Russian).

Legal sources

The Russian version contains the original legal excerpts and source links (in Russian). The inclusion of a rule does not make unique properties or enforcement-stage cases supported by this calculator.